The Building Regulations
Application Stage - How To Plan For The Design Process Of Your Home Extension - A clients guide.
After you have approved the construction design scheme with your home extension
architect or designer they will then be submitting the scheme on your behalf to the Council or other approved
imspector for checking and approving the full construction design and works.
During this application process a 'comments / query schedule' will be issued by the Checking
Inspector that will need attending to by your selected professional.
You should allow an 8 week period for this element of the design process.
During this application period you should also be submitting the scheme for tender prices from
selcted local builders.
|